Undersigning of settlement to the agreement on construction of units 5&6 at Opole Power Plant

106/2013

06.12.2013 17:20

Art. 56 section 1 p. 1 of Act on Public Offering – confidential information

Contents of the report

The Management Board of PGE Polska Grupa Energetyczna S.A. (“PGE”) discloses that on December 6, 2013 the Management Board of PGE Górnictwo i Energetyka Konwencjonalna S.A. ("PGE GiEK"), PGE subsidiary company, undersigned with Rafako S.A., Polimex-Mostostal S.A. and Mostostal Warszawa S.A. forming a syndicate (later referred to as the „General Contractor”), along with Alstom Power sp. z o.o. participation, a Settlement related to agreement for construction of units no 5&6 in Opole Power Plant.

In connection with the preparatory works regarding the Opole II project, on the ground of the Settlement the partners decided that the Notice To Proceed shall be issued to the General Contractor on January 31, 2014.

The settlement does not breach resolutions of the Agreement undersigned on February 15, 2012.

Signatures of persons representing the company

Date Name Position and function
2013-12-06 18:20:01 Piotr Szymanek p.o. Prezesa Zarządu
2013-12-06 18:20:01 Grzegorz Krystek Vice-President of the Management Board