Undersigning of settlement to the agreement on construction of units 5&6 at Opole Power Plant
106/2013
06.12.2013 17:20
Art. 56 section 1 p. 1 of Act on Public Offering – confidential information
Contents of the report
The Management Board of PGE Polska Grupa Energetyczna S.A. (“PGE”) discloses that on December 6, 2013 the Management Board of PGE Górnictwo i Energetyka Konwencjonalna S.A. ("PGE GiEK"), PGE subsidiary company, undersigned with Rafako S.A., Polimex-Mostostal S.A. and Mostostal Warszawa S.A. forming a syndicate (later referred to as the „General Contractor”), along with Alstom Power sp. z o.o. participation, a Settlement related to agreement for construction of units no 5&6 in Opole Power Plant.
In connection with the preparatory works regarding the Opole II project, on the ground of the Settlement the partners decided that the Notice To Proceed shall be issued to the General Contractor on January 31, 2014.
The settlement does not breach resolutions of the Agreement undersigned on February 15, 2012.
In connection with the preparatory works regarding the Opole II project, on the ground of the Settlement the partners decided that the Notice To Proceed shall be issued to the General Contractor on January 31, 2014.
The settlement does not breach resolutions of the Agreement undersigned on February 15, 2012.
Signatures of persons representing the company
Date | Name | Position and function |
---|---|---|
2013-12-06 18:20:01 | Piotr Szymanek | p.o. Prezesa Zarządu |