Result of main capacity market auction for the year 2030
45/2025
11.12.2025 11:22
Art. 17 ust. 1 Rozporządzenia MAR – informacje poufne
Contents of the report
The Management of PGE Polska Grupa Energetyczna S.A. (“PGE”) discloses that on December 11, 2025, as a result of capacity market auction for the year 2030 (the main auction), total capacity obligation of not less than 1 399.218 MW has been contracted for units owned by PGE Group, including 1 097.718 MW in 15-years contracts.
Including long-term contracts from previous auctions, PGE Group contracted not less than 7 738.971 MW of capacity obligations for 2030 delivery.
Auction clearing price has been set within the range between 465.03 and 511.51 PLN/kW/year and on the basis of article 38 par. 1 of the Capacity Market Act of December 8, 2017 the price will be disclosed by PSE S.A. within 3 business days.
The above information was prepared on the basis of the announcement of PSE S.A. informing about the close of the capacity market auction and does not constitute final results of the capacity auction.
Final results are to be published by the President of Energy Regulatory Office on its website (in the section Biuletyn Informacji Publicznej) on the first business day following 21st day after the close of capacity auction. Until then all capacity obligation contracts are conditional.
Signatures of persons representing the company
| Date | Name | Position and function |
|---|---|---|
| 2025-12-11 | Przemysław Jastrzębski | Vice-President of the Management Board |
| 2025-12-11 | Robert Kowalski | Vice-President of the Management Board |