Annex to the construction agreement regarding units 5 and 6 in Opole Power Plant.
25/2018
10.10.2018 11:53
Art. 17 sect. 1 of MAR – inside information.
Contents of the report
The Annex stipulates, inter alia:1. Amendment of the commissioning date of unit 5 to June 15, 2019 from May 31, 2019 previously envisaged in current report number 5/2018. The commissioning date of unit 6 remains intact, i.e. September 30, 2019 – in line with earlier estimates.2. Other technical and contractual amendments in favor of the Ordering Party.As a result of negotiations with the General Contractor, force majeure events occurred during over 4 years construction works period have been taken into account, so as additional works carried by General Contractor for the Ordering Party.
Parties of Agreement confirmed the amount of remuneration for the General Contractor on condition that dates of units commissioning agreed in the Annex are met.
Alignments involved in the Annex satisfies claims of both sides raised during the realization of the Agreement until the Annex date. The Ordering Party shall not raise claims against the General Contractor regarding exceeding the delivery date envisaged in the original version of the Agreement, before the Annex.
Signatures of persons representing the company